Our crew is currently working at a job in Tucson, Arizona moving buildings to create room for a new road that is being built. We just finished moving the second building and have five more to go. The first two buildings have been rolled to the back of the property and are being held there until a new foundation is poured for them to sit on. Moving this building took our crew about 13 days to complete everything from the preparation to the rolling and moving. Recently the weather has not been quite permitting, but we were able to continue working and get another house moved out of the way. We are now setting up to start working on moving the next house in about one and a half weeks. This is one of our bigger jobs that we will be spending quite a bit of time on and will continue to write updates and posts about our progress. Be sure to check out the rest of our posts and keep informed with our moves!